Walnut Creek Linear Trail Updates

  1. Overview
  2. Documents & Videos

wclt

PHASE 1:     Town Park to James McKnight Park East

  •  Passes through Katherine Rose Memorial Park, Hardy Allmon Soccer Complex and James McKnight Park West
  •  OPEN/Completed 2007

PHASE 2A:    Matlock Road to Phase 2B

  • Paved path around Elmer W. Oliver Nature Park for bike traffic

PHASE 2B:    Oliver Nature Park rear loop to 360 Tollway access road

  • Passes through Philip Thompson Soccer Complex
  • OPEN/Completed 2020

PHASE 2C:    360 Tollway to eastern city limits

PHASE 3A:    James McKnight Park East to Cannon/Carlin intersection

  •  Construction scheduled Feb 2021-late Summer 2021

PHASE 3B:    Cannon/Carlin intersection to Oliver Nature Park

  •  Widened sidwalks and safe crossings

PHASE 4A:    Town Park under Main Street/157 Bridge

PHASE 4B:    4A to western city limits

  •  Passes through Mans Best Field Dog Park